Step 1

- To initiate the process, please email solar@bartlettec.coop with your Member Application and Design attached.
- Please see BEC's DG Tariff and DG Procedures & Guidlines Manual for reference.

Step 2

- After receiving your application, BEC will apply a $200 application fee to your account.

Step 3

- Once payment is processed, BEC will begin reviewing your application and design. Permission to start the installation of the system will be granted upon approval.

Step 4

- After completing the construction phase, please email solar@bartlettec.coop to notify us that you are ready for the system inspection.

Step 5

- Within 10-12 business days, BEC will send a representative to conduct the inspection and perform a meter exchange, replacing it with a bi-directional meter for the system.

Step 6

- Finally, BEC will send a confirmation email stating that the inspection has passed and that you are authorized to operate the system on a specified date.