Step 1
- - To initiate the process, please email solar@bartlettec.coop with your Member Application and Design attached.
- - Please see BEC's DG Tariff and DG Procedures & Guidlines Manual for reference.
-
Step 2
- - After receiving your application, BEC will apply a $200 application fee to your account.
-
Step 3
- - Once payment is processed, BEC will begin reviewing your application and design. Permission to start the installation of the system will be granted upon approval.
-
Step 4
- - After completing the construction phase, please email solar@bartlettec.coop to notify us that you are ready for the system inspection.
-
Step 5
- - Within 10-12 business days, BEC will send a representative to conduct the inspection and perform a meter exchange, replacing it with a bi-directional meter for the system.
-
Step 6
- - Finally, BEC will send a confirmation email stating that the inspection has passed and that you are authorized to operate the system on a specified date.